Project Schedule
Initial Notice of Intent/Notice of Preparation
August 16, 2012
Scoping Meeting
August – October 2012
Scoping Comment Period
January 2013
Revised Notice of Preparation (for a Visitor Education Center, which since has been withdrawn from the Project)
January – March 2013
Second Scoping Comment Period (for the now withdrawn Visitor Education Center)
Spring 2013 – Winter 2015
Prepare Administrative Draft Environmental Impact Statement/Report (DEIS/EIR)
Spring 2015 – Mid-2017
Internal Agency Review & Revision of Administrative Draft EIS/EIR
Mid-2017
Release Draft EIS/EIR for Public Review
After DEIR/EIS Release
Public Comment Period, including Public Comment Meeting on the Draft EIS/EIR (specific date TBD)
Calfornia Department of Fish and Wildlife Update (10-3-2016)